Adana airport serves to domestic and international flights and its services were formerly offered in one building. After the completion of this project, the domestic and international services were separated. Furthermore, the standards of the services were improved by the construction of a new international terminal and car parking facilities. The turn-key delivery project which was contracted by the State Airports Operation Administration which included the construction of a 6,500 sqm terminal and a 9,000 sqm open car parking was completed in 6 months by Yüksel Construction Co.Inc. The electrical, mechanical, electromechanical and landscaping works were realized within the scope of this project which were taken in operation in February 1997.
 

    About Yüksel

 
   
 
 
 
   Adana Airport International Terminal Building and Miscellaneous Works / Adana
 
 Client   General Directorate of   State Airport Administration
 Location   Adana / Turkey
 Contract Date   07. 03. 1996
 Completion Date   10. 12. 1996