In the Alsancak port and passenger pier project, 1,717
concrete piles with 17 tons of weight and 30 m of length of each (total 51,510
m) were used. • 10.000 m² of existing steel piers were removed •
17,500 m² piled pier was constructed and • 205,000 m³ of dredge works
were carried out.