The Yanbu Power Plant Phase 2 project was undertaken to build and commision a power plant of 2 x 80 MW in Yanbu, near the existing SWCC Power and Desalination Plants Phase 1. Yüksel’s scope consisted of building concrete buildings (14,500 sqm) and steel buildings (2,000 sqm), concrete duct bank (5,000 m) tank foundations reinforced concrete chimney (13 m diameter and 93 m height), offices, roads, sewerage and installing potable water systems, lighting, landscaping and fencing. Moreover, Yüksel constructed 11 bachelor villas, 7 family villas and 1 restaurant for SWCC employers.
 

    About Yüksel

 
   
 
 
 
   Medine-Yanbu Desalination and Power Plant, Phase 2, Lot 1 / S. Arabia
 
 Client   Saline Water Conversion   Corporation (SWCC)
 Location   S. Arabia
 Contract Date   1990
 Completion Date   1999