Yüksel, having constructed many of the ports in Turkey and thus having been named as the leading port builder, constructed a 900 m. long pier at the depths of 6, 10, 14 m. within Aliağa Petrochemical Complex Port.

The project encompassed; • 3,000,000 tons of rock filling • 69,700 m³ of excavation on land • 558,500 m³ of excavation at sea • 11,000 m³ of rock excavation at sea • 63,100 m³ of concrete works • 49,500 m³ of quaywall concrete • 106,200 m² of mould works • 9,300 m² of levelling of sea bottom.
 

    About Yüksel

 
   
 
 
   Aliağa Petrochemical Complex Port / İzmir
 
 Client   Petkim Petrochemical
  Co.Inc.
 Location   İzmir / Turkey
 Contract Date   24. 10. 1975
 Completion Date   20. 02. 1979