The project which will help solve Ýstanbul’s
traffic problem between Taksim and Yenikapý has been awarded to “Anadolu
Metro Ortaklýðý” under the leadership of Yüksel
Construction Co., Inc.
The contract consists of two sections :
Taksim - Unkapanı Section This section includes 3,700 m. of bored
tunnel, 460 m. of Golden Horne Bridge Pass, 432 m. of viaducts, 54 m. of depressed
(with fill), 20 m. of cut and covered tunnel and 2 stations in Şişhane and
Unkapanı.
Unkapanı - Yenikapı Section This section includes 5,260 m.
of bored tunnel, 600 m. of cut and covered light rail system between Yenikapı
and Aksaray, 20 m. of depressed (with retaining wall) and 195 m. of cut and
cover tunnel sections. There are two stations in Yenikapı and Şehzadebaşı.
The Yenikapı Station is cut and covered and also is designed as a station
for the light rail metro. The Şehzadebaşı Station construction is bored tunnel
on the platform floors, while the entry and mezzanine floors are designed
as cut and covered.