TThe purpose of this project is to connect TEM highway
to GAP (South Anatolia Project). The highway consists of a 37 km. highway,
17 km. connection roads as well as 3 overpasses 150 m. long, 16 underpasses
192 m. long, a bridge of 40 m. of length and four (bridged type) junctions.
In the project, approximately 15,000,000 m³ of earth works, 156,000 m³ of
concrete, 1,256,000 tons of sub- base, 896,000 tons of mechanic stabilization
base and 762,000 tons of bituminous hot mix asphalt works were realized. The
project is undertaken by Makyol - Yüksel Partnership.