TThe purpose of this project is to connect TEM highway to GAP (South Anatolia Project). The highway consists of a 37 km. highway, 17 km. connection roads as well as 3 overpasses 150 m. long, 16 underpasses 192 m. long, a bridge of 40 m. of length and four (bridged type) junctions. In the project, approximately 15,000,000 m³ of earth works, 156,000 m³ of concrete, 1,256,000 tons of sub- base, 896,000 tons of mechanic stabilization base and 762,000 tons of bituminous hot mix asphalt works were realized. The project is undertaken by Makyol - Yüksel Partnership.
 

    About Yüksel

 
   
 
 
   Gaziantep - Şanlıurfa Motorway (Şanlıurfa - Suruç Section) / Şanlıurfa
 
 Client   General Directorate of
  Highways
 Location   Şanlıurfa / Turkey
 Contract Date   26. 06 1998
 Completion Date   In Progress