The Combined Cycle Plant which is located in Temelli-Maliköy, Ankara has an installed capacity of 770 MW. Yüksel is responsible for the civil construction works. During the 26 months construction period (95% in the first 12 months), 30,000 m³ concrete, 100,000 m³ excavation and 2,700 tons structural steel work had been carried out.

 

    About Yüksel

 
   
 
 
 
   Ankara Combined Cycle Power Plant / Ankara
 
 Client   Baymina Energy Co.Inc.
 Location   Ankara / Turkey
 Contract Date   15. 10. 2001
 Completion Date   31. 12. 2003