The Combined Cycle Plant which is located in Temelli-Maliköy,
Ankara has an installed capacity of 770 MW. Yüksel is responsible for
the civil construction works. During the 26 months construction period (95%
in the first 12 months), 30,000 m³ concrete, 100,000 m³ excavation
and 2,700 tons structural steel work had been carried out.
|
|||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||