Project is designed to treat the received water by chlorination method and transmit to Riyadh - Qassim water transmission system. Yüksel performed all kinds of civil works for the construction of electrical building, scraper building, chlorination building, CO2 tank shed, relief basin and pressure relief system. Design supply and construction of utility connections and site works such as; storm water channels, potable water line, fire alarm and fire fighting system as well as automatic control system for terminal facilities, irrigation system and roads were all under Yüksel’s line of responsibility.
 

    About Yüksel

 
   
 
 
 
   Al Jubail - Riyadh Line C Reservoirs and High Point Terminal / S. Arabia
 
 Client   Saline Water Conversion   Corporation (SWCC)
 Location   S. Arabia
 Contract Date   23. 05. 1993
 Completion Date   31. 12. 2001